Digging Up the Past: The Money Pit Deepens
By Teresa Rochester
Santa Monica's past has come back to haunt its already beleaguered multi-million
dollar Public Safety building, costing the city $1.2 million in clean
up, The Lookout has learned.
Debris from 80-year-old construction projects, leftover pieces of railroad
and soil contaminated by oil dumped at the site behind City Hall were
unearthed during excavation, which began in October of last year.
The discovery and removal of the debris dumped along a storm drain only
exacerbated a three-month delay caused when bids to complete phase one
of the project came in $10 million over budget in April.
"It certainly did complicate things," said City Manager Susan
McCarthy.
The removal of the rubble in the giant pit, which has sat idle and empty
since excavation was completed in May, also took a financial toll on the
118,000 square-foot facility's budget. City officials had budgeted $500,000
for the removal of debris; however clean up ultimately cost an additional
$700,000, City Engineer Tony Antich said.
Antich explained that removing debris and contaminated soil is more involved
that disposing of untainted fill. All of the material must be treated
for any environmentally harmful substances and must be disposed of at
specific sites.
City officials said they were surprised at the extent of the debris and
contaminated dirt. Antich said that soil samples taken at 50-foot intervals
failed to turn up anything. Between two of the holes where samples were
taken laid the trove of debris.
"As they [construction workers] were digging in the dirt, they discovered,
unbeknownst to them, remnants of piping, oil and contaminated soil,"
said Antich. "When the storm drain was built in the 20's and 30's,
the way they disposed of any excess construction material, they tossed
it next to the storm drain knowing it would be buried.
"We knew we had some contamination there," Antich said. "We
didn't have complete knowledge of the extent of things."
Along with the discarded construction materials, remnants of the old
railroad yard that used to occupy the site also were discovered. The majority
of the debris was finally removed as workers completed the excavation
in May.
McCarthy said that work would once again get underway at the site in
a few weeks, when construction crews begin working on the storm drain.
That project is expected to wrap up in the fall.
That's also when city staff, which has been negotiating with contractors,
is expected to present recommendations to the City Council after the bids
submitted for the construction of the project came in $10 million over
the $33 million budgeted for the building.
"It's a bull market for construction right now," said McCarthy.
"Staff is looking at a variety of ways to minimize the amount it
will be over our original budget."
The entire project, including equipment and furnishings for the building
that will house the city's fire and police departments and emergency services,
was originally budgeted at $43.7 million.
From the beginning the project has faced financial woes. In 1996, voters
narrowly shot down a $29.5 million bond to supplement $12.9 million set
aside by the council to fund the project. The vote marked the first time
in years that a local bond measure was turned down.
The following year, the council approved $43.7 million to build the facility.
Since the project's inception, plans for the building have undergone several
revisions to cut costs. Originally planned to be 119,000 square feet,
the facility will now have 118,000 square feet. The on-site jail that
was to accommodate 146 inmates will now hold 93.
The need for a new public safety facility became clear after the 1994
Northridge Earthquake devastated the city, causing a power outage in the
outdated 1950s police building that forced emergency response personnel
to set up operations in the parking lot.
The new building, touted as a model of environmentally friendly design,
will boast three large back-up generators that can power the facility
for 72 hours. The new building also will feature subterranean parking,
community rooms, a technically advanced evidence processing and identification
area and 15 conference rooms.
|